Executive summary
- The EBITDA margin of construction corporations reached 12.7% in 2025, the highest since 2006, yet 19.0% have negative equity and 31.3% made a loss [4].
- External supplies and services, which include subcontractors, weigh 44.3% of construction sales, against 25.2% for all companies [4].
- Construction collects in 70 days and pays in 81, with construction costs up 7.4% in September 2026 [4],[3].
- In public contracts subject to review, change orders totalled €675.8m in 2023–2025 and reached in 2025 their highest net level since 2006 [16].
- A Portuguese architect bills €35/h, against €71 in Europe, and two thirds of practices are one person [26].
- In Vektrum's base scenarios, a 25-person contractor gains €6,782 a year (+0.27 pp of margin) and releases €47,900 of cash; the assumptions are shown, and no cautious scenario pays back within five years.
01
Conclusions
Executive summary
Portuguese construction is going through record years. In 2024 there were 114,439 construction enterprises, with 460,416 people and €39,140m of turnover; gross value added grew 12.8% in one year [1]. In 2025 the EBITDA margin of construction corporations was 12.7%, the highest in a series that starts in 2006 (Vektrum calculation on BdP data) [4]. This report analyses general contractors, specialised trades, renovation, and architecture and engineering practices using official data from INE (Statistics Portugal), Banco de Portugal, Eurostat and the Court of Auditors, and turns the figures into decisions for SMEs with 8 to 30 people.
The central conclusion: the margin is healthy on average and fragile in the tail, and it is decided in processes that sit between the site and the office: progress measurements, change orders, subcontractor invoices, cash per job and unanswered client requests. That is where information reaches the decision-maker late, or never, and the sector starts from a low base: only 9.7% of Portuguese contractors have high or very high digital intensity, against 20.4% in the EU [13].
- EBITDA margin of construction corporations in 2025, the highest since 2006[4]
- 12.7%
- Construction corporations with a net loss (2025)[4]
- 31.3%
- Contractors with very low digital intensity (EU: 41.4%; 2025)[13]
- 58.4%
- Design fees in public procurement, as % of the works value (contract price)[27]
- 2.54%
Seven conclusions for management
- Record margin, fragile tail. Return on equity in construction was 13.2% in 2025, above the 9.1% of all companies, yet 19.0% of construction corporations have negative equity and 31.3% made a loss [4]. The average rewards those who control cost per job; the tail shows those who do not.
- A contractor buys in 44 cents of every euro it invoices. External supplies and services weigh 44.3% of sales, against 25.2% for all companies; with materials, they reach 68.5% [4]. The core competence is coordinating subcontractors, invoices, progress claims and deadlines, and that is where margin is lost.
- The sector is financed by its suppliers. It collects in 70 days and pays in 81, against 46 and 57 for all companies [4]. With construction costs up 7.4% year on year in September 2026, and materials up 7.2% [3], suppliers only need to shorten their terms for a cash gap to open.
- The brake is capacity, not demand. Only 3.9% of Portuguese contractors cite insufficient demand as a limiting factor, against 30.3% in the EU [14], and 90% of private-works firms surveyed by AICCOPN, the contractors' association, cite a shortage of skilled labour [21]. Caveat: in the European Commission's harmonised survey, labour shortage is cited by 24.7% in Portugal, below the EU's 26.4%, and 69.5% report no limiting factor at all [14]. The statement holds for firms with demand, not for the whole sector.
- Change orders in public works are at their highest since 2006. In 2025 the net increase was €204.4m; in 2023–2025, additional works totalled €675.8m, 11.8% of the initial price of the contracts that were changed [16]. The data cover only contracts subject to prior review by the Court of Auditors, but the lesson applies to any job: recording and billing variations on time is revenue.
- A Portuguese architect bills half the European hourly rate. The median hourly rate for an architect is €35, against €71 in Europe, and median income is 46% of the European average in purchasing-power terms; two thirds of practices are one person [26]. Each unbilled hour weighs more here than almost anywhere in Europe.
- AI has barely reached the site, and at a contractor the right automation pays through cash, not hours. 4.7% of Portuguese contractors with 10 or more people use AI, against 10.8% in the EU [11]. In our base scenarios, a 25-person contractor gains €6,782 net a year from cash per job and change-order capture (+0.27 pp of EBITDA margin) and releases €47,900 of cash once. A practice works differently: the €5,025 a year an 8-person practice gains from request qualification and meeting booking exists only if the hours freed are billed. These are Vektrum estimates, with the assumptions shown in chapter 6.
02
Structure
The sector: five business models
Construction accounts for 7.3% of non-financial enterprises, 9.3% of employment and 6.9% of turnover (2024). A construction enterprise has on average 4.0 people and €342.0k of turnover, and 48.3% are sole proprietorships [1]. Banco de Portugal estimates €43.5bn of turnover in the 12 months to June 2026, after the sector lost almost half its turnover between 2006 and 2016; the ratio of construction turnover to GDP, however, fell from 18% in 2006 to 14%. In the same study, 38% of workers were born abroad [5].
"Construction" hides business models that make money in different ways and lose margin in different places. We distinguish five.
- General building contractor (NACE 41). Earns the difference between the contract price and the cost of subcontractors, materials and its own crew. Margin leaks in the estimate (third-party costs misjudged), in variations carried out but not billed, and in the time between the progress claim and payment.
- Civil engineering and public works (NACE 42). Larger firms living on tenders, base prices and monthly progress claims. Margin is decided in the tender response, in the handling of additional contracts and in the dependence on the public investment cycle.
- Specialised trades (NACE 43): electrical, HVAC, plumbing, finishes. They sell crew hours and materials, often as subcontractors to a general contractor. Margin leaks in travel, unawarded quotes, late invoicing and the fact that they are paid only when the main contractor is paid.
- Renovation and refurbishment. It has no statistical code of its own: it is spread across NACE 41 and 43. It works mostly for private clients, on small jobs with many changes agreed on site. Margin leaks in site visits and quotes for requests that would never be awarded, and in changes agreed verbally. Licensed refurbishment fell 11.9% in Q2 2026 [2].
- Architecture (NACE 71.11) and engineering (NACE 71.12) practices. They sell professional hours, charged as a percentage of construction cost (38% of cases in Portugal), as a fixed lump sum (39%) or by the hour (11%) [26]. Margin leaks in hours that are never billed: proposals, client-requested revisions, coordination of the engineering disciplines and the sales work the architect does personally.
| Subsegment | Enterprises | People | Turnover (€m) | People per enterprise | Turnover per enterprise (€k) | Gross operating rate PT / EU (%) |
|---|---|---|---|---|---|---|
| Development and construction of buildings (NACE 41) | 51,215 | 208,070 | 17,204 | 4.1 | 335.9 | – |
| Civil engineering (NACE 42) | 3,263 | 60,531 | 7,959 | 18.6 | 2,439.2 | – |
| Specialised activities (NACE 43) | 53,376 | 161,777 | 10,342 | 3.0 | 193.8 | 11.8 / 13.9 |
| Architecture (NACE 71.11) | 10,514 | 17,335 | 744 | 1.6 | 70.8 | 19.5 / 27.5 |
| Engineering and related (NACE 71.12) | 19,270 | 46,465 | 3,581 | 2.4 | 185.8 | – |
Eurostat SBS. People and turnover per enterprise: Vektrum calculation. Gross operating rate = gross operating surplus ÷ turnover; for construction as a whole, 10.7% in Portugal against 12.1% in the EU. Eurostat includes sole proprietors, so totals differ from Banco de Portugal's, which covers corporations only. Sources: [7]
A sector of micro-firms, with few medium-sized ones
93.0% of construction enterprises have fewer than 10 people and 65.6% have 0 to 1 person; micro-firms account for 43.6% of employment and 32.2% of turnover, and only 830 enterprises have 50 or more people (2023, Vektrum calculation on Eurostat) [8]. Firms with 20 or more people carried out 58.2% of the value of work done in 2024, the highest share since 2011 [1]. Civil engineering is another world: 18.5 people per enterprise, against 3.0 in specialised trades (Vektrum calculation) [7].
In architecture and engineering (NACE 71), 97.1% are micro-firms and 82.4% have 0 to 1 person [8]. By the Architects' Council of Europe count, there are 4,695 architecture practices in Portugal, 3,080 of them one-person; a one-person practice turns over €29,009 a year on average and one with 6 to 10 people €300,893 [26]. A one-person practice has no back office: the architect is also the salesperson, the administrator and the collector.
| Construction (total) | 50% |
|---|---|
| Buildings (NACE 41) | 47% |
| Specialised trades (NACE 43) | 50% |
| Architecture (NACE 71.11) | 42% |
| Engineering (NACE 71.12) | 49% |
GVA per person employed, Portugal ÷ EU27. Vektrum calculation on Eurostat sbs_ovw_act. Sources: [7]
Portuguese construction generates €26.3k of GVA per person, against €52.2k in the EU; per hour worked, €17.3 against €40.9. It is also 25% below the average of Portugal's own business economy (€34.9k) [7]. Architecture has the widest gap: €21.2k per person against €50.6k in the EU. Globally, construction productivity grew about 1% a year in the two decades before 2015, against 2.8% for the economy and 3.6% for manufacturing, and the McKinsey Global Institute estimated that best practice could raise it by 50% to 60% [33]; it is a 2017 study with data to 2015, useful as an order of magnitude.
Market: housing rises, public works reverse
In Q2 2026 fewer buildings were licensed (−7.1%), but licensed new dwellings for family housing rose 10.8% to 11.8k, and completed dwellings rose 11.6% [2]. New mortgage lending totalled €23.4bn in 2025 (+34.9%), across 133,602 contracts [6]. Construction output grew 1.1% year on year in September 2026, after +2.0% in August; in the EU, +2.6% in August [15].
Public works peaked in 2025, with €7,568m of contracts signed (+48%). From January to September 2026, tenders fell 29% by value and 30% by number; contracts signed through open tender fell 52%, partly due to the base effect of the high-speed rail contract, and total contracts fell 43%; direct awards and prior consultations rose 32% [24]. Vektrum reading: for firms dependent on public works, 2027 calls for a private pipeline, and a private pipeline calls for a sales response that most construction SMEs have never had to organise.
03
Economics
Margins, costs and cash
The ratios in this chapter are Vektrum calculations on Banco de Portugal's Central Balance Sheet aggregates, which cover the 61,162 construction corporations, with 412,539 people (2025) [4]. They exclude sole proprietors and are weighted by size: they describe the sector, not the median SME. They are meant to read structure and trend, not to assess a specific company.
| Indicator | Construction | All companies |
|---|---|---|
| EBITDA margin (%) | 12.7 | 13.2 |
| Net margin (%) | 6.9 | – |
| External supplies and services (% of sales) | 44.3 | 25.2 |
| Goods and materials consumed (% of sales) | 24.2 | – |
| Staff costs (% of sales) | 22.7 | 17.0 |
| Return on assets (%) | 9.6 | 9.2 |
| Return on equity (%) | 13.2 | 9.1 |
| Equity ratio (%) | 39.2 | 45.3 |
| Average collection period (days) | 70 | 46 |
| Average payment period (days) | 81 | 57 |
BdP; margins and shares of sales: Vektrum calculation (item ÷ sales and services). Construction EBITDA margin was 11.8% in 2023 and 12.5% in 2024. Sources: [4]
| Sales and services | 100 € |
|---|---|
| External supplies and services (incl. subcontracting) | −44.3 € |
| Goods and materials consumed | −24.2 € |
| Staff costs | −22.7 € |
| Other income and costs (residual) | +3.9 € |
| EBITDA | 12.7 € |
Vektrum calculation on BdP data (construction corporations, 2025). The residual groups changes in production, work for own use and other operating income and costs. Sources: [4]
The fragile tail
- Construction corporations with negative equity (2025; 20.5% in 2018)[4]
- 19.0%
- Construction corporations with a net loss (2025; 32.6% in 2023)[4]
- 31.3%
- Corporations with financing costs above EBITDA (2025)[4]
- 11.8%
- Overdue loan ratio of construction firms (Q2 2026; 32% in 2015–2016)[5]
- 2%
The equity ratio rose from 30.9% in 2018 to 39.2% in 2025, and return on assets from 5.95% to 9.6% [4]. The sector is much sounder than ten years ago. But the improvement is in the average: almost one in five corporations still has negative equity, which is not insolvency, but leaves little room for a late payment or a badly estimated job. Against Europe, the gross operating rate in construction is 10.7% in Portugal against 12.1% in the EU, and 11.8% against 13.9% in specialised trades (2023) [7].
Cash: financed by suppliers
| Collection, construction, 2018 | 118 days |
|---|---|
| Collection, construction, 2025 | 70 days |
| Collection, all companies, 2025 | 46 days |
| Payment, construction, 2018 | 126 days |
| Payment, construction, 2025 | 81 days |
| Payment, all companies, 2025 | 57 days |
Banco de Portugal, Central Balance Sheet Database. Sources: [4]
Terms have shortened considerably since 2018, but remain 24 days above the rest of the economy, in both directions. Customers account for 16.6% of construction corporations' assets [4]. At sector level, each day of collection period is worth about €113m (sales ÷ 365, Vektrum calculation). In Intrum's survey, the average payment term in construction is 81 days, 34% above the national average, and about 31% fall between 101 and 200 days; press reports differ on whether the unit is receipts or companies [25]. In Q1 2025, 21% of public-works firms and 20% of private-works firms cited late payments as a constraint [23].
Costs: labour first, now materials too
- New housing construction cost, September 2026 year on year (first estimate)[3]
- +7.4%
- Labour component of the same index[3]
- +7.7%
- Labour cost in Portuguese construction (EU: €31.5/h; 2025)[9]
- €15.2/h
In November 2025 the index was up 4.8% (revised), with materials at +1.2% and labour at +9.1%: the pressure came from labour. In 2026 materials joined in; among the biggest increases in September were diesel (about 35%), copper wire (about 30%), bitumen (about 25%) and PVC pipes (about 20%) [3]. In Q2 2026, 52% of private-works firms cited production costs as a constraint, against 33% the previous quarter [21].
An hour of construction labour costs €15.2 in Portugal and €31.5 in the EU (2025); across the economy, €19.4 and €34.9 [9]. The minimum wage rose to €920 in 2026 (+5.7%) [20]. Per hour worked, construction generated €17.3 of GVA in 2023 [7]; the year differs from the labour-cost figure, so the comparison is only indicative, but it shows a thin gap between what an hour costs and what it produces. The construction job vacancy rate is 1.8% in Portugal, against 2.8% in the EU (2025) [10]. Vektrum hypothesis, not measured: the shortage shows up less as declared vacancies and more as jobs turned down.
Practices: cheap hours, compressed fees
| Indicator | Portugal | Europe-29 |
|---|---|---|
| Median hourly rate, partner (€) | 50 | 78 |
| Median hourly rate, architect (€) | 35 | 71 |
| Median hourly rate, technician (€) | 30 | 55 |
| Median full-time income, in PPP (€) | 19,864 | 43,461 |
| Fees as % of construction cost (% of jobs) | 38 | 35 |
| Fixed lump-sum fees (% of jobs) | 39 | 29 |
| Hourly fees (% of jobs) | 11 | 15 |
| Jobs without an agreed fee (%) | 3 | 2 |
Architects' Council of Europe, 2024 survey. Rates not adjusted for purchasing power; income adjusted for purchasing-power parity (€17,000 gross unadjusted). Sources: [26]
The median full-time income of Portuguese architects is the second lowest in Europe in purchasing-power terms, above only Romania [26]. On the AMADA report's status index, Portugal scores 0.93: architects earn less than the national average wage, whereas the average across the countries analysed is 1.13; and, in a single-family house case study, Portuguese architects budgeted 30% fewer design hours [29]. In public procurement, design fees came to 2.54% of the works value at contract price (3.37% at base price), across 236 procedures; in the 168 open, restricted and design competitions analysed, the contract price was on average 35.24% below the base price, and 51 of them, about 30%, were awarded below half the base price [27].
04
Diagnosis
Where margin is lost
There are no published Portuguese data on time spent per estimate, award rates in renovation, response time to client requests, or the share of a practice's hours that is never billed. That is itself a finding: most SMEs in the sector do not measure these costs, because they are spread across the days of several people. What follows combines indirect official indicators, international studies with their scope stated, and what we see in the field.
Seven loss points
- Cash per job. With 70 days to collect and 81 to pay [4], each job's cash position changes every week, yet it is common for the treasury plan to live in an Excel sheet updated by hand and for bank reconciliation to be done at month-end. 11.8% of construction corporations have financing costs above EBITDA [4]. Vektrum reading: delays often stem from invoices issued late or collections nobody followed up, not from the client.
- Progress measurements and change orders. In public contracts subject to prior review, additional works totalled €675.8m in 2023–2025, more than in the previous 12 years (€592.4m), across 1,197 contracts at 265 public bodies. They amount to 11.8% of the initial price of the contracts that were changed; net of €114.3m of omitted works (work removed from the contract, not amounts refused by the Court), the net increase is 9.79%. Infraestruturas de Portugal, the national road and rail operator, accounts for 48.62% of the total [16]. The data include only contracts above the review threshold and do not represent private or small works. In private work, the typical loss is different: changes agreed on site and recorded days later, or never, which do not reach the next progress claim.
- Estimating. In public works, "excessive competition / abnormally low prices" (26%) and "tender base price too low" (20%) were the second and third constraints in Q4 2025 [22]; in private works, unfair competition (21%) and excessive competition (19%) in Q2 2026 [21]. In a survey of 724 owners and contractors in the US, Canada, the UK and Australia/New Zealand, 33% of typical projects came in over budget, and more than 1 in 5 of the best ones too [32]. Since 68.5% of the price is third-party cost [4], a 1 pp error in estimated cost equals about one seventh of the sector's average net margin (Vektrum calculation: 1 ÷ 6.9).
- Responding to renovation and design requests. We found no verifiable Portuguese data on response time to enquiries or conversion rates, and the most-cited American study on the subject could not be confirmed in the original; it was left out of this report. What the data show is active demand (licensed new dwellings +10.8% [2]; new mortgage lending +34.9% [6]) and scarce capacity. The cost, therefore, is not losing requests: it is spending the scarce hours of a partner, architect or site manager on 2 to 3-hour visits, travel included, to requests that would never be awarded (Vektrum estimate).
- Rework. The Get It Right Initiative literature review cites the Construction Industry Institute (2005): direct rework costs average 5% of total construction cost, in a range of 0% to 25%; other authors put it at 3% to 15% of contract value [31]. In the 2018 FMI/PlanGrid survey of about 600 professionals, mostly in the US, 52% of rework globally was attributed to poor project data and communication (48% in the US) [30]. These are Anglo-Saxon studies from before 2023: they are an order of magnitude, not Portuguese data.
- Information and documents. In the same survey, site teams spent 35% of their time on non-optimal activities: 13.4% (5.5 hours a week) looking for project information, 11.6% resolving conflicts and 9.6% dealing with errors and rework [30]. In Portugal there is also compliance: at the end of H1 2025 there were 68,501 valid contractor licences, 37,529 permits (alvarás) and 30,972 certificates, and classes 1 and 2 made up 80% of the permits [17]. Every subcontractor must have licences, insurance and tax and social-security clearances up to date; Vektrum reading: at SMEs, checking them is mostly manual. Municipal licensing was cited as a constraint by 16% to 20% of private-works firms between Q4 2023 and Q1 2025 [23].
- Unbilled architecture hours. There is no recent Portuguese or European source on the share of a practice's time that goes into proposals, competitions or unpaid revisions. There are indirect signs: sole practitioners work 46.2 hours a week and 3% of jobs have no agreed fee [26], and Portuguese architects budget fewer design hours than European ones [29]. Vektrum reading: in a small practice, the first meeting, scheduling, reminders and each client's notes consume hours of the same partner who then has to design.
05
Levers
Opportunities by subsegment
4.74% of Portuguese contractors with 10 or more people use AI, against 10.79% in the EU; in 2024 the figures were 2.74% and 6.09%. Across all Portuguese companies, 11.54%: construction is below half of its own economy's average. In legal, accounting, consulting, architecture and engineering services, 20.06% against 37.92% in the EU [11]. Construction is the sector with the lowest AI adoption in the EU (10.79%, against 62.52% in information and communication) [12]. And 58.4% of Portuguese contractors have very low digital intensity, against 41.4% in the EU; only 9.7% have high or very high intensity (EU: 20.4%) [13].
In a business where 44 cents of every euro invoiced goes on external supplies and services [4], the concrete opportunity lies in the flows of documents and decisions that already pass through the company every day and today depend on someone remembering. We organise it into four levers: revenue (picking the right requests and responding fast), margin (billing every change and estimating with real costs), cost (fewer hours retyping invoices, progress claims and reports) and capital (collecting progress claims faster and seeing each job's cash every day).
| Subsegment | Revenue | Margin | Cost | Capital |
|---|---|---|---|---|
| General contractor | Faster estimates built from past jobs | Changes recorded on the day and billed in the next claim | Subcontractor invoices read and allocated to the job | Daily cash per job and bank reconciliation |
| Public works and civil engineering | Tender screening against past awards | Additional contracts documented with site evidence | Site diary from voice and photos | Progress claims ready at month-end |
| Specialised trades | Same-day response to quote requests | Hours and materials per job against the estimate | Timesheets and delivery notes read without retyping | Invoice at each phase, not at the end of the job |
| Renovation | Request qualification before the visit | Changes approved in writing by the client | Standard estimate from price databases | Stage payments tied to job milestones |
| Architecture and engineering practices | Single request entry point and direct booking | Hours per stage logged and compared with the fee | Meeting briefings and notes generated automatically | Stage invoices issued when the stage closes |
Vektrum synthesis. Three of these opportunities are quantified in chapter 6.
Contractors: capital before hours. With about €113m of sales per day across the sector (Vektrum calculation on BdP data) [4], each day less in collections is worth more than many administrative hours. In a company turning over €2,500,000 a year, one day of collection period is about €6,800.
Practices: BIM is coming, but the margin lies around it. The BIM obligation for RJUE architecture projects from 1/1/2030 stands; above the threshold in article 474(3)(a) of the Public Contracts Code, projects must "whenever possible" be modelled in BIM [19],[28]. The PortugalBIM Strategy has a 6-year implementation period and IMPIC, the construction regulator, had 90 days to present an action plan [18]. In 2024, 42% of Portuguese architects used BIM frequently, 66% used 3D modelling and only 8% used coordination and clash-detection tools [26]. Vektrum reading: BIM is a design tool; the margin opportunities in this report lie in the sales process, the documents and the cash around it.
06
Quantification
Impact scenarios
The following scenarios apply the official data to two typical profiles and separate data (with a source) from Vektrum assumptions. Every result is calculated from the assumptions shown. The aim is not to promise a return but to show the order of magnitude and the point at which each automation pays off, including the cases where it does not.
On change orders: the only public ratio is the Court of Auditors', 11.8% of the initial price of public contracts that were changed [16]. We use it as a ceiling, not an average, and assume only part is lost and only part of that loss is recovered.
| Indicator | Contractor or specialised trade | Design practice |
|---|---|---|
| People | 25 | 8 |
| Estimated turnover | €2,500,000 | €300,893 |
| Reference EBITDA margin | 12.7% | 19.5% |
| Reference EBITDA | €318,175 | €58,674 |
| Reference net income | €171,787 | – |
Vektrum calculation. Contractor: sales per person of construction corporations (BdP 2025) × 25, with the sector's aggregate EBITDA and net margins, dominated by larger firms. Practice: average turnover of a Portuguese architecture practice with 6 to 10 people (ACE 2024), with the gross operating rate of architecture (Eurostat 2023) as a proxy for the EBITDA margin. Sources: [4],[26],[7]
Profile A: contractor or specialised trade, 25 people
Assumptions
- Bank reconciliation hours saved per month4 / 6 / 8Vektrum estimate
- Active jobs with a treasury plan6 / 8 / 10Vektrum estimate
- Hours per job per month updating the plan by hand2Vektrum estimate
- Reduction of update time50% / 60% / 70%Vektrum estimate
- Loaded cost of one administrative hour[9]19.4 €/hOfficial
- Reduction of the collection period[4]5 days / 7 days / 10 daysVektrum estimate
- Upfront investment€10,000 / €8,000 / €6,000Vektrum estimate
- Annual running cost (hosting, licences, support)€2,400 / €1,800 / €1,200Vektrum estimate
- Reference EBITDA margin[4]12.7%Vektrum calculation
| Result | Cautious | Base | Favourable |
|---|---|---|---|
| Hours freed per year | 120 | 187 | 264 |
| Annual value of the hours | €2,328 | €3,632 | €5,122 |
| Cash released (once) | €34,200 | €47,900 | €68,500 |
| Annual running cost | €2,400 | €1,800 | €1,200 |
| Net annual gain | −€72 | €1,832 | €3,922 |
| Upfront investment | €10,000 | €8,000 | €6,000 |
| Effect on EBITDA margin | −0.003 pp | +0.07 pp | +0.16 pp |
| Increase in current EBITDA | −0.02% | 0.6% | 1.2% |
| First-year ROI | Does not pay back | −77% | −35% |
| Three-year ROI | Does not pay back | −31% | 96% |
| Payback | Does not pay back | 52.4 months | 18.4 months |
ROI and payback count only the value of hours. The cash released enters the bank once and is not included in ROI; its annual value depends on each company's cost of financing. The 5 to 10-day reduction assumes faster collection of progress claims already approved, not clients paying earlier of their own accord. The three scenarios combine the low, central and high values of each assumption, in the order shown. The value of hours assumes the time freed is redeployed to useful work; if it is not, the cash effect is smaller. First-year ROI includes the full investment; three-year ROI is undiscounted. Replace the assumptions with your company's figures.
Assumptions
- Change orders as % of turnover[16]6.0% / 9.0% / 11.8%Vektrum estimate
- Share not billed or billed more than 30 days late10% / 15% / 25%Vektrum estimate
- Part of that loss that is never billed40% / 50% / 60%Vektrum estimate
- Share of never-billed work recovered by same-day recording (photo, measurement, approval)30% / 40% / 50%Vektrum estimate
- Upfront investment€12,000 / €10,000 / €8,000Vektrum estimate
- Annual running cost (hosting, licences, support)€2,400 / €1,800 / €1,200Vektrum estimate
- Reference EBITDA margin[4]12.7%Vektrum calculation
| Result | Cautious | Base | Favourable |
|---|---|---|---|
| Revenue recovered per year | €1,800 | €6,750 | €22,125 |
| Annual running cost | €2,400 | €1,800 | €1,200 |
| Net annual gain | −€600 | €4,950 | €20,925 |
| Upfront investment | €12,000 | €10,000 | €8,000 |
| Effect on EBITDA margin | −0.02 pp | +0.20 pp | +0.84 pp |
| Increase in current EBITDA | −0.2% | 1.6% | 6.6% |
| First-year ROI | Does not pay back | −51% | 162% |
| Three-year ROI | Does not pay back | 49% | 685% |
| Payback | Does not pay back | 24.2 months | 4.6 months |
The upper change-order share (11.8%) is the Court of Auditors' ratio for public contracts subject to review that were changed; it is not representative of private work and is used only in the favourable case. Only work that would never be billed counts as margin: it has already been carried out and paid for, so the revenue recovered goes straight to profit. The part billed late is not margin but cash that arrives sooner, and it is not counted here. The three scenarios combine the low, central and high values of each assumption, in the order shown. The value of hours assumes the time freed is redeployed to useful work; if it is not, the cash effect is smaller. First-year ROI includes the full investment; three-year ROI is undiscounted. Replace the assumptions with your company's figures.
Profile B: design practice, 8 people
Assumptions
- Client requests per month25 / 35 / 45Vektrum estimate
- Minutes of screening and back-and-forth per request20 / 25 / 30Vektrum estimate
- Reduction of that time with a qualifying form and direct booking50% / 60% / 70%Vektrum estimate
- First meetings avoided per month with unqualified requests2 / 3 / 4Vektrum estimate
- Hours per avoided meeting, travel included2.0 / 2.5 / 3.0Vektrum estimate
- Value of one hour freed (cost; architect rate; partner rate)[9],[26]27.4 €/h / 35.0 €/h / 50.0 €/hVektrum calculation
- Upfront investment€9,000 / €7,500 / €6,000Vektrum estimate
- Annual running cost (hosting, licences, support)€2,400 / €1,800 / €1,200Vektrum estimate
- Reference margin (gross operating rate of architecture)[7]19.5%Official
| Result | Cautious | Base | Favourable |
|---|---|---|---|
| Hours freed per year | 98 | 195 | 333 |
| Annual value of the hours | €2,685 | €6,825 | €16,650 |
| Annual running cost | €2,400 | €1,800 | €1,200 |
| Net annual gain | €285 | €5,025 | €15,450 |
| Upfront investment | €9,000 | €7,500 | €6,000 |
| Effect on EBITDA margin | +0.09 pp | +1.67 pp | +5.13 pp |
| Increase in current EBITDA | 0.5% | 8.6% | 26.3% |
| First-year ROI | −97% | −33% | 158% |
| Three-year ROI | −90% | 101% | 673% |
| Payback | Over 60 months | 17.9 months | 4.7 months |
The cautious case values the hour at cost (Eurostat, professional, scientific and technical activities, 2025); the others at the median billed rate of an architect and a partner (ACE 2024), which holds only if the hours freed are sold. It excludes the effect of faster response on award rates, for which there is no verifiable Portuguese data. The three scenarios combine the low, central and high values of each assumption, in the order shown. The value of hours assumes the time freed is redeployed to useful work; if it is not, the cash effect is smaller. First-year ROI includes the full investment; three-year ROI is undiscounted. Replace the assumptions with your company's figures.
| Profile | Net annual gain | Effect on EBITDA margin | Increase in current EBITDA | Cash released (once) |
|---|---|---|---|---|
| Contractor, 25 people | €6,782 | +0.27 pp | 2.1% | €47,900 |
| Design practice, 8 people (if the hours freed are billed) | €5,025 | +1.67 pp | 8.6% | – |
Vektrum estimate: for the contractor, the sum of the two base scenarios; for the practice, the base scenario, which values each hour freed at an architect's median rate and so only materialises if those hours are sold.
07
Experience
What Vektrum is building
Here we show what we are building and proposing in this sector, with the status of each piece of work stated. We do not publish client names or results: one piece of work is in progress, another is a proposal, and the third was delivered in another sector. The impact figures in this report come from the cited sources and the scenarios in the previous chapter, not from these cases.
Vektrum case
In progressDesign practice for single-family houses
A practice designing single-family houses wants requests to come in through one channel, meeting booking to stop depending on message exchanges and each client's information to live in one place. Pilot in the final stage of implementation.
What was built
- Website form as the single entry point for requests, with qualifying fields (area, own home, plot)
- Direct meeting booking synchronised with the team's calendars, with rules for slots, durations and notice
- Single client record with history and notes per meeting
- Briefing generated automatically before each meeting from the request's history
- Recording of in-person meetings, transcribed and stored on the client record
- Confidentiality by design: data kept in a closed circuit, with restricted access
What we learned
- Start from the sales process (what each meeting must leave on record), not from the tool.
- Confidentiality was designed in from day one: where the data live, who sees them and how they leave the system.
Work in progress: there are no measured results yet and we present none.
Vektrum case
ProposedProperty development and construction company
Proposal submitted, not delivered. A property development and construction company with active jobs manages cash per job in Excel, with formulas it uses for business-plan sensitivities. The proposal automates feeding that plan from the banks and invoicing, without replacing Excel.
What was built
- Read-only Open Banking connection to the bank accounts
- Own database with daily extraction of transactions
- Matching of bank transactions to invoices from the existing invoicing platform or ERP, by amount, description and IBAN, including one payment covering several invoices; ambiguous cases go to human review
- Automatic feeding of the per-job treasury plan in Excel, keeping the formulas used for business-plan sensitivities
- Daily treasury dashboard by job, with actual vs business plan and alerts
- Natural-language querying of the data via Claude, read-only
What we learned
- The fragile parts are real bank transaction descriptions and preserving the existing Excel formulas; a pilot should start with them.
At proposal stage: none of this has been delivered.
Vektrum case
Transferable capabilitySupplier-invoice reading and cost-centre allocation
A system that reads supplier invoices, suggests which cost centre they belong to and organises validation, while keeping control with the finance team. At a contractor, the cost centre is the job.
What was built
- Reads the AT (Tax Authority) QR code first, with local OCR as fallback; no invoice is sent to external AI services
- Cost-centre, or job, suggestion for each invoice
- Validation queues for invoices with doubts or discrepancies
- Audit log of every change
Developed and delivered for a condominium management company, an adjacent sector, not a contractor or a practice. It is presented as a transferable capability; it is not a case from this sector.
Sector-specific ideas
- Site diary from voice and photos: the site manager dictates and takes photos; the system organises them by job, work front and date, and flags changes that should go into the next progress claim.
- Progress-claim workflow: measurements, photos and client approvals in one record, with the claim prepared at month-end and the invoice issued on the day of approval.
- Estimating assistant: from price databases and past estimates, proposes items, quantities and starting prices for the estimator to review, and flags materials with the steepest recent price rises.
- Subcontractor document compliance: permits, insurance and tax and social-security clearances with tracked expiry, and an alert before a subcontractor goes on site with an expired document.
- Job margin before close-out: supplier and subcontractor invoices allocated to the job on the day they arrive, compared with the estimate.
- Hours per stage in a practice: light time logging per project and stage, compared with the fee, to learn which kinds of project make money.
08
Priorities
Action plan
The matrix ranks eleven actions by impact, effort and horizon. The rule is to start with what can be measured in weeks, using the systems the company already has (Excel, invoicing, email, calendar), and only then move to what depends on an organised history.
Impact
EffortLow → High
0 to 30 days
- 1
Measure the baseline
Two weeks of logging: requests received and useful meetings, changes agreed vs billed, bank reconciliation time.
Impact 2/3 · Effort 1/3 · 0 to 30 days
- 2
Same-day change recording
Photo, measurement and client approval for each change on the same day, in a folder or form per job.
Impact 3/3 · Effort 1/3 · 0 to 30 days
- 3
Qualifying request form
A single entry point with area, type of work, timing and indicative budget before any visit.
Impact 2/3 · Effort 1/3 · 0 to 30 days
- 4
Subcontractor compliance
Document list with expiry dates and an alert before going on site.
Impact 2/3 · Effort 1/3 · 0 to 30 days
30 to 90 days
- 5
Direct meeting booking
Linked to the team's calendars, with rules for slots, durations and notice.
Impact 2/3 · Effort 2/3 · 30 to 90 days
- 6
Automatic bank reconciliation
Transactions read daily and matched to invoices, with ambiguous cases for human review.
Impact 2/3 · Effort 2/3 · 30 to 90 days
- 7
Cash per job
Excel treasury plan fed automatically, without losing existing formulas.
Impact 3/3 · Effort 2/3 · 30 to 90 days
- 8
Supplier-invoice reading by job
AT QR code and local OCR, with job suggestion and human validation.
Impact 2/3 · Effort 2/3 · 30 to 90 days
90 to 180 days
- 9
Progress-claim workflow
Claim prepared from the month's records and invoice issued on the day of approval.
Impact 3/3 · Effort 2/3 · 90 to 180 days
- 10
Voice and photo site diary
Start on one job with one site manager; measure time before and after.
Impact 2/3 · Effort 2/3 · 90 to 180 days
- 11
Estimating assistant
Depends on organised past estimates; start with one type of job.
Impact 3/3 · Effort 3/3 · 90 to 180 days
09
Method
Assumptions and limitations
Every figure in this report comes from a research dossier verified on 16/11/2026, in which each number was checked against its primary source; Banco de Portugal and Eurostat series were downloaded and recalculated. Numbers that could not be confirmed were excluded. Ratios marked as Vektrum calculations are arithmetic on cited official series; Vektrum estimates are our own assumptions, stated in each scenario.
- Different universes. INE and Eurostat include sole proprietors (about 114k construction enterprises) [1]; Banco de Portugal covers corporations only (about 61k) [4]. Financial ratios come from BdP and size figures from INE and Eurostat; they are not mixed in the same calculation.
- Reference years. Productivity and structure use 2023, Eurostat's latest complete year for Portugal [7]; financial ratios use 2025. The September 2026 cost index is a first estimate, subject to revision [3].
- Change orders. The Court of Auditors' data cover only public contracts subject to review that were changed [16]. They do not describe private or small works.
- Labour shortage. AICCOPN's 90% comes from a survey of its members [21]; the European Commission's harmonised survey, with a different question and sample, gives 24.7% for Portugal [14]. We present both.
- International benchmarks. The studies on rework, site information, budget overruns and productivity [30],[31],[32],[33] come from Anglo-Saxon markets and pre-date 2023. The Intrum survey was read via the press [25].
- Gaps. We found no published Portuguese data on time per estimate, award rates in renovation, response time to requests or the share of unbilled hours in practices. Request volumes, minutes per task, active jobs, change-order losses, reductions in collection time, investment and running cost are Vektrum estimates and should be replaced with your company's data.
Sources
Every figure in the report points to a numbered source. Vektrum calculations and estimates are labelled as such.
- [1]Construction Enterprises 2024 (15/12/2025)INE · 2025 · Official source
- [2]Construction: licensed and completed works, Q2 2026 (11/9/2026)INE · 2026 · Official source
- [3]New Housing Construction Cost Index, September 2026 (9/11/2026)INE · 2026 · Official source
- [4]BPstat, annual economic and financial indicators of construction corporations (Central Balance Sheet Database)Banco de Portugal · 2026 · Official source
- [5]Construction in Portugal: what has changed in the last 20 years? (4/11/2026)Banco de Portugal · 2026 · Official source
- [6]Credit Markets Monitoring Report 2025 (June 2026)Banco de Portugal · 2026 · Official source
- [7]Structural business statistics, sbs_ovw_actEurostat · 2026 · Official source
- [8]Structural business statistics by size class, sbs_sc_ovwEurostat · 2026 · Official source
- [9]Hourly labour costs, lc_lci_levEurostat · 2026 · Official source
- [10]Job vacancy rate, jvs_a_rate_r2Eurostat · 2026 · Official source
- [11]Use of artificial intelligence in enterprises, isoc_eb_ain2 and isoc_eb_aiEurostat · 2026 · Official source
- [12]Statistics Explained, Use of artificial intelligence in enterprisesEurostat · 2026 · Official source
- [13]Digital intensity by activity, isoc_e_diin2Eurostat · 2026 · Official source
- [14]Business and consumer surveys, construction, ei_bsbu_m_r2Comissão Europeia / Eurostat · 2026 · Official source
- [15]Production in construction, sts_copr_mEurostat · 2026 · Official source
- [16]Report 1/2026 – OAC, 1st Section, Additional Contracts 2023-2025Tribunal de Contas · 2026 · Official source
- [17]Construction Sector Report for Portugal, first half of 2025IMPIC · 2025 · Official source
- [18]Council of Ministers Resolution 89/2026 (PortugalBIM Strategy)Diário da República · 2026 · Official source
- [19]Decree-Law 108/2026 of 29 May (amending the RJUE and article 17 of Decree-Law 10/2024), text published by the Ordem dos ArquitectosOrdem dos Arquitectos · 2026 · Official source
- [20]National minimum wage for 2026 set at €920 (Decree-Law 139/2025)APCMC · 2025 · Official source
- [21]Sector Situation Survey, Q2 2026AICCOPN · 2026 · Study
- [22]Sector Situation Survey, Q4 2025AICCOPN · 2026 · Study
- [23]Sector Situation Survey, Q1 2025AICCOPN · 2025 · Study
- [24]Public Works Barometer no. 153 (October 2026)AICCOPN · 2026 · Study
- [25]Late payments between companies stabilised, but construction shows significant problems (Intrum, European Payment Report 2025)Jornal Económico · 2025 · Press
- [26]The Architectural Profession in Europe 2024, Sector StudyArchitects' Council of Europe · 2025 · Study
- [27]2nd Report on Fees in Public Procurement in Portugal 2023–2025Ordem dos Arquitectos · 2025 · Study
- [28]PortugalBIM technical noteOrdem dos Arquitectos · 2026 · Study
- [29]AMADA Report 2025, Beyond Passion: The Devaluation of Architects in 21st-Century EuropeAMADA · 2025 · Study
- [30]Construction Disconnected (2018)FMI / PlanGrid · 2018 · Vendor
- [31]Literature Review, Financial and economic impact of errorGet It Right Initiative · 2018 · Study
- [32]The Construction Cost Management Report (c. 2020)Dodge Data & Analytics / Procore · 2020 · Vendor
- [33]Reinventing construction: A route to higher productivity (2017), summary on Designing Buildings WikiMcKinsey Global Institute · 2017 · Study
Methodology
Sources: INE, Banco de Portugal (Central Balance Sheet Database, via BPstat), Eurostat and the Court of Auditors for Portuguese and EU data; the Official Journal and the text of Decree-Law 108/2026 published by the Ordem dos Arquitectos for the legal framework [18],[19]; sector associations, professional bodies and international studies identified as such, with their scope stated. All sources were accessed on 16/11/2026.
Verification: every number in the underlying dossier was checked against its primary source; derived ratios were recalculated from the original series. Values that could not be confirmed, or existed only in secondary summaries, were excluded from the report.
Vektrum calculations: ratios (item ÷ sales and services), people and turnover per enterprise, sales per day (sales ÷ 365) and Portugal/EU comparisons are arithmetic on published series, with the formula stated.
Scenarios: hours freed = monthly volume × 12 × minutes ÷ 60 × reduction; value = hours × hourly cost or rate; cash released = turnover ÷ 365 × days; change orders recovered = turnover × change-order share × share lost × part never billed × share recovered (the part billed late is cash, not margin); margin effect = (value − running cost) ÷ turnover. All results are calculated in code from the published assumptions.
Limitations: sector aggregates are dominated by larger firms; international benchmarks do not describe the Portuguese SME; there are no published Portuguese data on estimating, response to requests or unbilled hours in practices.